Digi Power X: Alabama AI data centre on track as NeoCloudz revenues flow

Digi Power X Inc (NASDAQ:DGXX) CEO Michel Amar said the first phase of its Alabama AI data centre with Cerebras remains on schedule, with long-lead items secured. The modular system has run on NVIDIA B300 GPUs since 15 May. He cited $95-100M self-funded capex and about $155M cash, and plans to add 50MW co-location by 2027.

Original reporting
Published Jul 9, 2026, 6:15 PM UTC
Analysis
alphai AI DeskAI-generated
Added to alphai Jul 9, 2026, 6:27 PM UTC. Informational, not investment advice.
How this was made
alphai summarizes source reporting and applies a structured AI analysis for relevance, timing, sentiment and ticker impact. Always verify material claims with the original publisher.
Digi Power X: Alabama AI data centre on track as NeoCloudz revenues flow — source image
Decision brief

The 30-second read

$DGXXBullishMed
01

Why it matters

If the Alabama modular system remains operational and AI revenues scale, it can shift the market’s valuation from mining economics to AI infrastructure growth. However, the article does not provide revenue figures, margins, or customer commitments, limiting immediate fundamental repricing.

02

Market read

Traders get a fresh operational milestone (May 15 uninterrupted GPU run) plus funding/capex and expansion plans, which can influence near-term positioning in AI infrastructure plays.

03

What to watch

Key risks include execution on the planned 50MW co-location and 10MW GPU build, dependence on NVIDIA hardware availability, and whether the New York power asset evaluation translates into funded, timely upgrades.

Relevance 6/10Novelty 6/10Timing: today, CEO interview highlights current operational status and funding position

Background

Digi Power X is transitioning from Bitcoin mining toward AI data center infrastructure, using a GPU bare-metal rental and GPU-as-a-Service model.

Company-level read

Ticker impact

$DGXXBullishMedium confidence
Context

Digi Power X says its Alabama AI data center phase 1 is on schedule and running on NVIDIA B300 GPUs since May 15.

Expected impact

Moderate upside bias if investors view the GPU-as-a-Service ramp and revenue generation as credible and scalable.

Evidence & confidence

The article provides specific operational timing (May 15 uptime) and capital/cash figures, but lacks revenue magnitude, customer contracts, or financial guidance to quantify impact.

Market effects

Reinforces demand narrative for GPU bare-metal rental and AI data center co-location, potentially supporting sentiment across AI infrastructure providers.

Could be read as incremental AI capacity build-out in the US Southeast, though the article does not quantify local economic impact.

GPU supply and AI compute capacity remain global constraints; the claim of uninterrupted NVIDIA B300 operations may resonate with broader AI infrastructure themes.

Counterpoint

AI revenue generation is asserted but not quantified; investors may discount the claim without disclosed customer contracts, pricing, or audited financial impact.

Key entities

  • Digi Power X Inc

    CEO Michel Amar discusses Alabama AI data center progress, GPU uptime, and AI revenue generation via NeoCloudz.

  • NVIDIA

    Hardware referenced as NVIDIA B300 GPUs running continuously since May 15.

  • Cerebras

    Referenced for the first phase of the Alabama project.

  • NeoCloudz

    Referenced as the AI revenue generation platform.

Related articles

$DGXXMedAI 9/10

Digi Power X Stock Rallies After $35M Nvidia Vera Rubin Commitment - Digi Power X (NASDAQ:DGXX)

Digi Power X said it committed $35 million to acquire Nvidia Vera Rubin rack-scale systems, with initial deployment targeted for Q1 2027 subject to Nvidia’s delivery schedule. The company plans to fund the purchase with cash on hand and offer capacity via NeoCloudz. It also updated that its Phase 1 (15 MW) AI data center is on track for Dec. 15, 2026, with grid interconnection and a power agreement completed. DGXX shares were up 6.36% to $8.36.

$000660.KSMedAI 8/10

SK Hynix is spending $38 billion to build two new chip fabs

SK Hynix said it will invest 54 trillion won (about $38 billion) to build two new DRAM and NAND fabs, Y2 in Yongin and M17 in Cheongju, as part of a broader 700 trillion won plan. Construction for Y2 starts July 2027, with a first cleanroom by June 2029. M17 construction begins Feb 2027, first cleanroom Dec 2028. The company cited strong HBM and NAND demand.

$BABAMed

Alibaba plans revenue sharing for major users of Qwen AI model

Reuters reports Alibaba will require major users of its upcoming open-source Qwen 3.8-Max AI model to negotiate commercial licenses and share revenue from products built with the model. The revenue share rate is not yet set, and the measure may be introduced next week. The plan follows Moonshot’s Kimi K3 licensing, which can require paid deals and up to 30% revenue sharing.