SCC orders Dominion to develop tariff to assign more transmission costs to data centers
Virginia’s State Corporation Commission ordered Dominion Energy to develop a tariff/policy to assign more transmission infrastructure costs to data centers and other large-load users. The order follows Dominion’s “rider T1” rate case and Gov. Abigail Spanberger’s administration input. Dominion sought $1.5 billion recovery, about a $0.94 monthly average increase, and the final outcome depends on a future SCC ruling.
How this was made
The 30-second read
Why it matters
The SCC ordered Dominion to propose a policy/tariff to assign transmission infrastructure costs to data centers and other large-load customers, aiming for a “symmetrical” approach. The commission also acknowledged the tariff may not address every reliability-related transmission cost instance. Dominion sought recovery of $1.5 billion, but the article says it is unclear when the SCC will rule on the new tariff and what the exact residential savings will be.
Market read
Traders in regulated utilities may reprice regulatory risk around transmission cost recovery as regulators push more grid costs onto data centers rather than residential customers.
What to watch
The order notes the new tariff may not cover all reliability-driven transmission cost cases, leaving potential residual cost allocation disputes and future rider adjustments.
Background
The SCC’s decision comes from Dominion’s rate adjustment case for its “rider T1,” which covers transmission line and substation build costs, amid rapid data center load growth in Virginia.
Ticker impact
Virginia’s SCC ordered Dominion Energy to develop a tariff that directly assigns transmission costs to data centers and other large-load users.
Near-term: modest, as the order is a policy directive but the final tariff timing and quantified residential impact are unclear.
The article describes an SCC order to develop a cost-allocation policy within Dominion’s “rider T1” framework, but it does not confirm final rates or when implementation will occur.
Market effects
Sets a precedent for cost allocation in utility transmission planning tied to large-load data center growth.
Could reduce cross-subsidization concerns for Virginia residential customers while affecting data center development economics in Northern Virginia.
Limited direct global impact, but it reinforces a broader regulatory trend of shifting grid costs to high-load users.
Counterpoint
Even if costs are reallocated, Dominion’s total allowed revenue may not fall materially; the main change could be who pays rather than the utility’s earnings power.
Key entities
- companyDominion Energy
Subject of the SCC order to develop a transmission-cost tariff for data centers and other large-load users.
- regulatorState Corporation Commission (SCC)
Ordered Dominion to develop the cost-assignment policy/tariff for transmission infrastructure.
- government_officialAbigail Spanberger
Governor who said the order should save Virginians hundreds of millions and that data centers should pay their full transmission infrastructure cost.





