Texas Energy Giant Oncor Supports Governor's Data Center Freeze
Oncor, a Sempra subsidiary, said on an earnings call that about 44 GW of large-load projects in its Texas service area qualified for ERCOT’s “Batch Zero” interconnection process, but Gov. Greg Abbott ordered a pause on new data center approvals pending a statewide audit. ERCOT put Batch Zero reviews on hold pending clarification. Oncor service requests rose to 298 GW. Sempra reported a $65B capex plan through 2030 and $560M base rate revenue approved for Oncor.
How this was made

The 30-second read
Why it matters
Gov. Abbott’s order paused new data-center interconnection approvals pending a statewide audit, and ERCOT reportedly put Batch Zero review on hold pending clarification. Oncor executives still cite strong service-request growth and indicate capital plan impacts are deferred to at least 2027.
Market read
Traders should monitor whether the Abbott moratorium expands or changes ERCOT’s Batch Zero timeline, since it can shift the timing of load-driven grid buildout and related regulatory filings.
What to watch
Oncor’s current $47.5B capital plan excludes Batch Zero-related spending, so near-term earnings risk may be muted; the bigger swing factor is whether regulators allow cost recovery for any resulting study or delay-driven capex.
Background
ERCOT introduced a new “Batch Zero” interconnection process for large loads (75 MW+), with criteria finalized in June, intended to sequence generation and load growth.
Ticker impact
Sempra’s Oncor, a subsidiary, faces ERCOT Batch Zero review uncertainty after Gov. Abbott paused new data-center interconnection approvals.
Stock impact likely limited unless the moratorium expands or delays Oncor’s approved capex and rate recovery timeline.
The article cites a state order pausing approvals and ERCOT putting Batch Zero review on hold, but also states Oncor’s current capital plan excludes Batch Zero spending and updates are deferred to Q4 with impacts not until at least 2027.
Market effects
Texas utility and grid-planning risk premium may rise for large-load interconnection timelines, affecting sentiment around regulated transmission and load-growth narratives.
ERCOT-area data-center and transmission development schedules could face additional delays, influencing regional power infrastructure expectations.
Limited direct global impact, but it reinforces policy-driven variability in grid interconnection processes for large-load demand.
Counterpoint
The moratorium may ultimately tighten and clarify interconnection rules, reducing long-run uncertainty and supporting a more durable framework that benefits Oncor’s pipeline.
Key entities
- utilityOncor
Texas electric transmission and distribution utility, a Sempra subsidiary, whose large-load interconnection pipeline is affected by the Batch Zero pause.
- parent_companySempra
Parent company of Oncor; provides earnings-call commentary on interconnection pipeline durability and capital planning.
- grid_operatorERCOT
Texas grid operator implementing Batch Zero review; reportedly paused Batch Zero review pending governor clarification.
- governmentTexas Gov. Greg Abbott
Ordered a pause on new data-center interconnection approvals pending a statewide audit.
- regulatorPublic Utility Commission of Texas (PUCT)
Approved Oncor’s $560M base rate increase effective June 1, providing some regulatory support amid interconnection uncertainty.


