Fermi Inc. shares rose 21.68% to $7.16 after the company said it signed its first binding 15-year turnkey data-center lease at Project Matador in Texas with TensorWave. The deal covers 222 MW and is projected to generate about $6.5 billion in contracted revenue, with first phase delivery in H2 2027.
How this was made

The 30-second read
Why it matters
The TensorWave lease is the first binding commercial agreement and provides a concrete revenue anchor ($6.5B contracted over the initial term) tied to 222 MW of power capacity, which can materially change perceived project risk.
Market read
Traders can reprice Fermi’s probability-weighted project completion and tenant conversion after a binding lease, while monitoring for follow-on leases ahead of the Aug 13 earnings release.
What to watch
The article notes prior volatility from financing and litigation, so traders may discount the lease’s impact until management provides clearer guidance on remaining capacity fill rates and capital requirements into 2H 2027.
Background
Fermi is building Project Matador, a large privately developed power campus in Texas, and has faced leadership transition and securities litigation alongside financing activity.
Market effects
Reinforces demand signals for AI power infrastructure and hyperscale data-center buildouts, potentially improving sentiment for other grid, power, and data-center infrastructure plays.
Highlights Texas power capacity and data-center development momentum, which may attract additional tenant interest in the region.
Supports the broader AI infrastructure capex narrative, which can influence cross-border financing and supply-chain expectations for power and compute facilities.
Counterpoint
A single binding lease may not fully validate the economics of filling the campus; execution risk remains until additional tenants sign and power delivery timelines are met.
Key entities
- companyFermi Inc.
Energy infrastructure company building Project Matador; stock surged after announcing its first binding customer lease.
- customerTensorWave
AI cloud provider signing a 15-year turnkey data-center lease at Project Matador.
- projectProject Matador
Flagship Texas power campus intended to support large-scale AI data centers.
- supplierSouthwestern Public Service Company (Xcel Energy subsidiary)
Power supply agreement referenced as covering up to 200 MW capacity to the site.