Pipeline for $165 Billion Oracle Data Center Delayed to Next Year
Energy Transfer’s Transwestern unit said in a filing that the Green Chile gas pipeline feeding Oracle’s Project Jupiter in New Mexico was delayed, with an in-service date set for Feb. 1, 2027 instead of Aug. 15. New Mexico land commissioner Stephanie Garcia Richard twice rejected the route citing water and emissions. Oracle shares fell about 4% on Friday, Energy Transfer rose 1.4%.
How this was made

The 30-second read
Why it matters
A regulatory-driven slip of nearly six months to the pipeline’s in-service date increases schedule uncertainty for Project Jupiter, aligning with Oracle’s prior warning to FERC that delays jeopardize broader objectives.
Market read
The filing changes a concrete infrastructure milestone for Oracle’s Project Jupiter, and the article reports a same-day Oracle share drop tied to the delay.
What to watch
The article attributes the delay to state land commissioner refusals; traders may need to monitor whether appeals, route redesign, or additional approvals could restore the original August timeline.
Background
The Green Chile pipeline is intended to supply gas to Oracle’s Project Jupiter in Doña Ana County, New Mexico, supporting a 2.5GW AI data center plan with Bloom Energy fuel cells.
Ticker impact
Oracle’s Project Jupiter pipeline delay pushes the in-service date to Feb 1, 2027, risking timing for its 2.5GW AI data center buildout.
Near-term downside bias versus a no-delay scenario, with magnitude likely limited unless further regulatory or construction slippage emerges.
The article cites Oracle’s own FERC filing that “time is of the essence,” and reports a same-day ~4% Oracle share drop alongside the delay disclosure.
Market effects
Highlights permitting and environmental constraints for gas-fed power and fuel-cell-backed data center infrastructure, potentially affecting timelines for other AI power projects.
New Mexico land and emissions objections add regulatory friction for large energy and infrastructure builds in the state.
Reinforces that AI data center expansion is increasingly constrained by energy, water, and emissions permitting, not just compute supply.
Counterpoint
The pipeline delay may be partially offset by Oracle’s fuel-cell compromise and expanded Bloom order, so operational impact could be less severe than the headline implies.
Key entities
- companyOracle
Tenant and project lead for Project Jupiter AI infrastructure in New Mexico, cited as facing schedule risk from the pipeline delay.
- companyEnergy Transfer (Transwestern unit)
Filed with federal regulators that the Green Chile pipeline in-service date moved to Feb 1, 2027.
- government_officialStephanie Garcia Richard
New Mexico land commissioner who refused the route twice, citing water use and emissions concerns.
- regulatorFederal Energy Regulatory Commission (FERC)
Regulator referenced via Oracle’s May filing warning that time is of the essence.