NVIDIA Backs OpenAI’s Gigantic 8GW Ohio AI Mega-Campus In Restructured Deal
NVIDIA finalized a land, power and shell guarantee for OpenAI’s Pike County, Ohio AI data center, restructuring its initial financing commitment from 4.25 IT-GW to cover the first phase, with an option to extend to 8 IT-GW. SB Energy will build and operate the facility under a 20-year lease to OpenAI, with NVIDIA as exclusive compute provider. NVIDIA also plans a $1.5B equity investment in SB Energy. Capacity starts in phases from 2028.
How this was made

The 30-second read
Why it matters
NVIDIA’s finalized LPS guarantee and $1.5B equity investment clarify near-term financing scope (first phase) while preserving an option to extend to the full site later, with capacity phased from 2028.
Market read
A concrete, NVIDIA-specific infrastructure financing structure is disclosed, including a reduced initial commitment, an extension option, and a large equity check, which can shift expectations for AI capex risk and compute demand durability.
What to watch
The article does not quantify the residual-value commitments or the exact scope of lease and power payments, so traders may be underestimating tail risk versus the headline $1.5B equity figure.
Background
OpenAI sought infrastructure loan backing for a large Pike County, Ohio data center; NVIDIA’s support was initially discussed as a much larger guarantee before being restructured.
Ticker impact
NVIDIA finalized an LPS financial guarantee for OpenAI’s Ohio AI data center and will invest $1.5B equity into SB Energy for the project.
Near term: supportive for AI-infrastructure narrative, but investors may discount residual risk from the restructured guarantee and potential larger long-run spend.
The article discloses a concrete, company-specific financing structure change (cut initial commitment, option to extend) plus a $1.5B equity investment, which can move expectations for capital intensity and risk. It also notes a prior investor reaction (stock down 5%) tied to earlier, larger proposed guarantees, implying sensitivity to downside risk.
Market effects
Reinforces the trend of GPU vendors underwriting AI infrastructure (land, power, shell) to secure long-duration compute demand.
Highlights major Ohio grid and data-center buildout via SB Energy and the PORTS-Pike Technology Campus, with phased capacity starting in 2028.
If replicated, could increase competition for power and site capacity, affecting AI capex planning across hyperscalers and GPU supply chains.
Counterpoint
The restructured guarantee may signal higher perceived risk or tighter investor appetite, and the option to extend coverage could still leave NVIDIA exposed to future cost overruns.
Key entities
- public_companyNVIDIA
Finalized LPS financial guarantee for OpenAI’s Ohio AI campus and made a $1.5B equity investment into SB Energy.
- private_companyOpenAI
Tenant of a 20-year lease for the PORTS-Pike Technology Campus, aiming to reduce reliance on third-party hyperscalers.
- private_companySB Energy
Builds, owns, and operates the facility under a 20-year lease to OpenAI; receives NVIDIA equity investment.
- projectPORTS-Pike Technology Campus
The newly named site in Pike County, Ohio, where phased capacity is scheduled to come online starting in 2028.