i-80 Gold (IAUX) Q2 2026 Earnings Call Transcript
i-80 Gold (IAUX) held its Q2 2026 earnings call, discussing progress at Granite Creek Underground and Archimedes. Granite Creek Q2 production rose to about 8.6k oz gold, with YTD about 17.5k oz, on track for 2026 guidance of 30k to 40k oz. Updated Granite Creek resource supports a feasibility study planned for Q3 2026; Archimedes first gold is targeted for Q4 2026.
How this was made

The 30-second read
Why it matters
Traders can use the disclosed Q2 production, unit mining costs, inventory build at the third-party facility, and updated feasibility timing to gauge the probability of meeting 2026 guidance and the risk of cost or schedule slippage.
Market read
The transcript provides actionable operating metrics and guidance reaffirmation, plus specific operational and schedule risks that can drive near-term estimate changes.
What to watch
Third-party processing availability reduced processing volumes versus mine output, which could recur and pressure recoverable ounces even if mine grades improve.
Background
The article is a transcript of i-80 Gold’s Q2 2026 earnings call covering underground ramp-ups, processing constraints, and feasibility-study timelines across multiple projects.
Ticker impact
i-80 Gold reported Q2 2026 production of about 8.6k ounces and reiterated 2026 guidance of 30k to 40k ounces.
Mildly positive bias for the next few sessions, with volatility tied to whether Q3 grades/tonnes improve as guided.
The transcript provides concrete production, cost, and guidance numbers plus specific operational constraints (ground conditions, third-party processing inventory, rig availability) that can drive revisions.
Market effects
Adds another data point on ramp-up execution and third-party processing bottlenecks for underground gold developers.
No clear regional macro linkage beyond general gold demand exposure.
Limited; company-specific guidance and project milestones rather than a broad gold-market catalyst.
Counterpoint
The guidance reaffirmation may mask underlying delays, since Archimedes drilling is expected to extend into early next year and feasibility timing shifts.
Key entities
- companyi-80 Gold
Reported Q2 2026 production, unit mining costs, and reiterated 2026 guidance, with project updates for Granite Creek Underground, Archimedes, Cove Underground, and Mineral Point Open Pit.
- projectGranite Creek Underground
First producing project in the ramp-up phase; management cited restored access after ground-condition impacts and expects improved Q3 grades/tonnes.
- projectArchimedes
Underground development progressing toward first gold mined from the upper 426 zone in Q4 2026; oxide opportunity and drilling campaign delays discussed.