Riot Signs $28 Billion AI Data Center Lease for 910 Megawatts
Riot Platforms signed a 15-year, $28 billion data-center lease with an AI lab, expanding beyond Bitcoin mining. The deal covers 910 MW of capacity, adding to 1,151 MW under contract. Q3 revenue was $181 million, up 1%, while net income fell to $4.03 million. Bitcoin mining revenue declined 28%.
How this was made

The 30-second read
Why it matters
A large, long-duration lease can change valuation by improving revenue visibility and reducing dependence on Bitcoin price and mining margins, but traders will likely focus on lease terms and funding needs not provided here.
Market read
Material new contract scale for Riot, with potential to shift expectations from mining-only earnings toward contracted data-center cash flows.
What to watch
Mining revenue is still declining in the article, and the lease’s impact depends on construction timelines, power costs, and whether contracted revenue is truly insulated from utilization risk.
Background
Riot is a Bitcoin miner that is increasingly building contracted data-center capacity to diversify revenue as mining economics fluctuate.
Ticker impact
Riot Platforms signed a 15-year, $28 billion lease for 910 MW of AI data-center capacity, expanding its contracted data-center revenue base.
Likely upward bias as investors price in longer-duration contracted revenue and reduced earnings volatility from mining.
The article discloses large, multi-year capacity and contracted revenue figures, which can re-rate the business mix, but it lacks details on economics, funding, and customer identity.
Market effects
Reinforces the trend of Bitcoin miners monetizing power and facilities via AI/data-center leases, potentially tightening competition for capacity.
No specific geography is provided, limiting near-term regional read-through.
Supports broader AI infrastructure demand narrative, but the customer is unnamed so global supply-chain implications are limited.
Counterpoint
The unnamed AI lab and lack of lease economics could mean execution or demand risk, so the market may discount the revenue quality.
Key entities
- companyRiot Platforms
Signed a 15-year, $28B data-center lease covering 910 MW of IT capacity, expanding contracted revenue.