Oracle Stock Falls 4% as HSBC Sells $300M Loan in Mid-80s
Oracle (ORCL) stock fell 4% as HSBC sold $300M of Project Jupiter data center debt at a discount, raising concerns about financing costs. Oracle traded at $114.34, down from $119.09. HSBC sold its portion of the $18B financing package at mid-80s cents on the dollar. Oracle issued a force majeure notice due to construction delays.
How this was made

The 30-second read
Why it matters
Bloomberg’s report that HSBC sold its roughly $300M holding at mid-80s cents on the dollar adds a concrete datapoint to secondary-market pressure and renews concerns about construction delays, permitting, and financing economics for Oracle’s AI infrastructure expansion.
Market read
Traders may reassess Oracle’s AI infrastructure financing risk as lender exits at discounts become visible, potentially affecting near-term sentiment and credit-spread expectations.
What to watch
Other tranches and contractual protections could price differently; the article notes the force majeure notice does not prove cancellation or imminent default.
Background
Oracle’s Project Jupiter is a major AI data-center campus in New Mexico, funded by an approximately $18B construction financing package arranged in late 2025, with Oracle as principal tenant and Blue Owl Capital as developer.
Ticker impact
Oracle shares fell about 4% after Bloomberg reported HSBC sold roughly $300M of Project Jupiter construction debt at mid-80s cents on the dollar.
Likely continued downside pressure as the market extrapolates higher financing risk and longer timelines for Project Jupiter.
The article links the reported lender exit price and Oracle’s force majeure notice to renewed scrutiny of construction economics, and the stock is already trading down on the disclosure.
Market effects
Highlights tightening credit conditions and wider dispersion in pricing for AI data-center construction debt, which can raise funding costs for the sector.
New Mexico data-center project financing scrutiny may affect sentiment toward large-scale power and permitting-dependent infrastructure builds.
Signals broader European and global banks’ willingness to sell AI infrastructure exposures at discounts, potentially influencing cross-border funding availability.
Counterpoint
The HSBC sale is a single lender’s exit and may not reflect realized losses or default risk across the entire $18B financing package.
Key entities
- companyOracle
US-listed issuer whose stock fell after reported discounted sale of Project Jupiter construction debt tied to its AI data-center expansion.
- financial_institutionHSBC
Reportedly sold about $300M of Project Jupiter construction debt at mid-80s cents on the dollar.
- projectProject Jupiter
New Mexico AI data-center campus within Oracle’s Stargate expansion, subject to energy and permitting delays and a force majeure notice.
- developerBlue Owl Capital
Developer associated with the Project Jupiter force majeure notice and equity commitments referenced in the article.