MARA Raises $185 Million to Fund Long Ridge Power Plant Deal
MARA raised $185 million via 8.750% senior secured notes due 2032 to fund its acquisition of Long Ridge Energy, a 505 MW gas plant. Proceeds will also repay part of Long Ridge's debt and cover fees. The offering is expected to close on November 27, 2026, alongside the acquisition. MARA has reduced its total debt by $1.4 billion in 2026 and authorized a $500 million share repurchase program.
How this was made

The 30-second read
Why it matters
The issuance provides earmarked funding for the Long Ridge deal and partial debt repayment, with both the notes settlement and acquisition close expected on Nov. 27, 2026.
Market read
Traders can monitor the Nov. 27 close as the key catalyst, while also tracking leverage optics from the new secured notes and the asset-backed power thesis.
What to watch
Deal closing conditions and integration of the 505 MW plant could dominate the credit story; the article does not quantify expected cash-flow contribution or power price assumptions.
Background
MARA is a bitcoin miner pursuing vertical integration into power generation via the Long Ridge Energy acquisition, after FERC authorization.
Ticker impact
MARA priced $185 million of 8.750% senior secured notes to fund its Long Ridge Energy acquisition, with closing expected Nov. 27.
Likely modest support as the market prices in deal funding and regulatory clearance, but with risk around closing conditions and incremental leverage.
The article discloses a specific debt issuance size, coupon, and expected close date tied to the acquisition, plus FERC authorization. It does not provide MARA’s equity price reaction, so direction is inferred from financing clarity versus execution risk.
Market effects
Highlights the growing use of power-generation assets to reduce electricity cost volatility for bitcoin miners, potentially reinforcing the sector’s asset-backed strategy.
PJM grid participation and FERC authorization underscore regulatory gating for power-related expansion in US grid regions.
US power infrastructure and grid access remain a key constraint for global mining economics, influencing broader miner cost curves.
Counterpoint
The notes are additional secured leverage, so the market may view the transaction as increasing fixed obligations rather than improving risk.
Key entities
- companyMARA
Bitcoin miner issuing $185 million of 8.750% senior secured notes due 2032 to fund the Long Ridge Energy acquisition.
- companyLong Ridge Energy
Owner of a 505 MW combined-cycle natural gas power plant being acquired by MARA, with existing 8.750% notes under the same indenture.
- regulatorFederal Energy Regulatory Commission (FERC)
Authorized the acquisition as consistent with the public interest.