New York trust acquires Amazon data centers in Madison County
Blackstone Digital Infrastructure Trust (BXDC) is acquiring a 75% stake in two Amazon Web Services (AWS) data center campuses, including one in Madison County, for $5 billion. The deal, announced on Nov. 16, includes 13 data centers across two campuses. AWS will retain a 25% interest and lease back the properties for up to 32 years. The transaction is expected to close by year-end, with AWS responsible for taxes, insurance, and maintenance.
How this was made

The 30-second read
Why it matters
For BXDC, the key tradable elements are deal size, ownership split, lease duration, and who bears taxes and operating costs. For Madison County, the key uncertainty is whether the end of the FILOT tax break and the $292 million assessment versus AWS’s $69 million contention leads to litigation outcomes that could affect local optics and potentially deal economics.
Market read
This is a concrete, deal-specific disclosure for BXDC with long-duration contracted income, but it also surfaces a local property-tax dispute that could create interim headline risk before closing.
What to watch
The article notes AWS’s FILOT tax break expires after 10 years and that AWS and the county disagree on assessed values; traders may need to watch for any court filings or settlement language that could affect net cash flows.
Background
The piece describes a $5 billion agreement where Blackstone Digital Infrastructure Trust will acquire controlling interest in AWS data-center campuses, including a Madison County mega site, with a long triple-net leaseback to AWS.
Ticker impact
Blackstone Digital Infrastructure Trust (BXDC) is the deal vehicle, announcing a $5 billion agreement to gain controlling interest in AWS data centers in Canton and Indiana.
Likely modest positive bias as investors price in accretive, contracted data-center income, tempered by uncertainty around closing and Madison County tax litigation.
The article is centered on BXDC’s acquisition announcement, including $5 billion consideration, 75% ownership, 12-year triple-net leaseback with options, and AWS retaining 25% interest. It also flags a property-tax break ending and assessment challenges, which can create near-term overhang even if AWS remains responsible for taxes under the agreement.
Market effects
Reinforces ongoing hyperscale data-center monetization via REIT-style vehicles and long leaseback structures, while highlighting local tax and permitting friction.
Madison County’s property-tax assessment dispute could drive local political and legal headlines even if AWS bears operating/tax costs under the lease.
Supports the broader AI data-center capex and financing narrative, but the impact is primarily localized to the specific campuses and counterparties.
Counterpoint
If Madison County litigation materially changes effective tax burden or delays closing, the deal’s risk-adjusted yield could be less attractive than the headline economics suggest.
Key entities
- companyBlackstone Digital Infrastructure Trust Inc.
Announced the acquisition agreement to gain controlling interest in AWS data-center campuses and will own 13 constructed centers across two AWS campuses.
- companyAmazon Web Services (AWS)
Counterparty providing the data centers, retaining 25% interest in joint ventures, and leasing back the portfolio on a triple-net basis while remaining responsible for taxes and operating expenses.
- governmentMadison County Board of Supervisors
Approved the property tax assessor’s $292 million valuation for the AWS buildings, with AWS able to challenge in circuit court.