Applied Digital signs USD 5.4 billion AI data centre lease with unnamed hyperscaler
Applied Digital signed an 18-year, USD 5.4 billion lease with an unnamed investment-grade hyperscaler for 150 MW of AI data center capacity. The deal could reach USD 12.7 billion if all renewals are exercised. This brings the company's total contracted base-term lease revenue to over USD 41 billion. Delivery is expected to start in the first half of 2028, pending development milestones and regulatory approvals.
How this was made
The 30-second read
Why it matters
The lease adds a large, creditworthy contract, with about 75 percent of contracted base-term revenue tied to investment-grade customers.
Market read
A large contract award that raises contracted revenue and supports the AI data centre growth case, with delivery and funding risks.
What to watch
Funding relies on the Macquarie equity partnership and project loans not yet arranged.
Background
Applied Digital is a US data centre company that signed a 15-year, 210 MW lease worth about USD 5.2 billion earlier this year at its Delta Forge 2 site.
Ticker impact
Signed 150 MW lease with unnamed investment-grade hyperscaler, expected to generate USD 5.4 billion over an 18-year base term.
Likely supportive as contracted revenue grows, with execution risk on 2028 delivery and financing remaining the key offset.
The article discloses a new lease with better pricing than prior deals. Delivery depends on power, approvals and funding through Macquarie and project loans.
Market effects
Confirms continued hyperscaler demand for long-term AI data centre capacity.
Primarily US data centre market.
Limited direct global relevance.
Counterpoint
The tenant is unnamed and 2028 delivery depends on power supply, approvals and construction, so timing risk remains.
Key entities
- companyApplied Digital
US data centre company that signed the 150 MW lease.
- companyMacquarie Asset Management
Partner in a USD 5 billion equity partnership to fund the build.