Fortuna Mining authorises $250 million of project contracts and reports Q3 2026 results

Fortuna Mining Corp. released its third‑quarter 2026 financials, showing $90.8 million of free cash flow and production of 69,665 gold‑equivalent ounces. The board gave management permission to sign project contracts worth $250 million to keep the Diamba Sud construction schedule on track. The company also announced the acquisition of the Bambadji exploration project in Senegal and received a notice of admissibility for the Diamba Sud exploitation permit, which it expects to be granted in the fourth quarter of 2026.

The $250 million contract authority enables Fortuna to secure equipment and services before the permit is issued, supporting its construction timeline. The acquisition expands Fortuna’s land package in a high‑grade gold corridor, potentially increasing future production and cash flow.

  • 1Free cash flow from operations for Q3 2026 was $90.8 million, a quarter‑over‑quarter increase of $5.1 million.
  • 2Adjusted attributable net income for the quarter was $51.2 million, or $0.17 basic EPS.
  • 3Gold‑equivalent production in Q3 2026 totaled 69,665 ounces.
  • 4The board approved management to sign project contracts totaling $250 million over the life of the Diamba Sud project.
  • 5Fortuna acquired the 190 km² Bambadji gold exploration project for $200.0 million in cash and a 0.5% net smelter return royalty on the first 1.75 million ounces produced.
  • 6Senegal’s Ministry of Mines issued a Notice of Admissibility for the Diamba Sud exploitation permit on November 2 2026, with final approval expected in Q4 2026.