Finland orders Google to halt construction at two AI data centers over missing environmental assessments

Finland's Licensing and Supervision Agency (LVV) issued a stop‑work order to Google subsidiary Tuike Finland Oy for the data‑center projects in Muhos and Kajaani. The agency said work such as tree felling, excavation and road building proceeded without a required environmental impact assessment and must cease by Oct. 23. Google said it fell short of its own standards, will follow the guidance and will re‑plant trees on 130 hectares at Muhos. The projects are part of a planned €13 billion (≈$15 billion) AI‑infrastructure investment through 2028.

The halt could delay the rollout of new AI capacity and affect Alphabet’s 2026 capex guidance, which was raised to $195 billion‑$205 billion after the investment announcement. Investors will watch the assessment timeline for any further impact on the company’s AI build‑out schedule.

  • 1Finland’s LVV ordered a suspension of construction at the Muhos and Kajaani sites until environmental impact assessments are completed by Oct. 23.
  • 2The suspension covers activities such as tree removal, excavation, quarrying, ditching and road construction.
  • 3Google’s subsidiary Tuike Finland Oy will comply and plans to plant trees across 130 hectares at Muhos.
  • 4The two sites are part of a €13 billion (≈$15 billion) AI‑infrastructure investment announced for 2027‑2028.
  • 5Alphabet raised its 2026 capital‑expenditure guidance to $195 billion‑$205 billion, up from $180 billion‑$190 billion.
  • 6More than 300 hectares of forest were cleared at the Muhos site, which the agency said required an assessment before work began.
  • Material 1 cites a €13 billion investment, while materials 2‑6 refer to a $15 billion (or $15.13 billion) figure.
  • Material 1 mentions over 300 hectares cleared; material 6 describes 740 acres (≈300 hectares) of forest cleared.