Vizsla Silver postpones first Panuco production to the second half of 2028

Vizsla Silver announced that the start of silver output at its Panuco project in Sinaloa, Mexico, is now expected in the latter half of 2028, a full year later than previously planned. The delay is attributed to ongoing permitting, site‑readiness and construction schedule issues, as well as heightened security concerns after the January 2026 attacks. Engineering work is roughly 50% complete and about 85% of processing‑plant equipment has been ordered, but a formal production decision has not yet been taken. The company also pledged US$5 million to a new community foundation in the region.

The later start pushes back cash‑flow generation and may affect the timing of capital returns, so investors will need to reassess project economics under the new schedule. Vizsla’s commitment of US$5 million to a community foundation signals continued spending on social initiatives despite the delay.

  • 1First production at Panuco is now targeted for the second half of 2028, instead of the second half of 2027.
  • 2Initial capital expenditure remains US$238.7 million as per the November 2025 feasibility study.
  • 3Engineering is about 50% complete.
  • 4Approximately 85% of the processing‑plant equipment has been ordered.
  • 5Vizsla has pledged US$5 million to establish a community foundation.
  • 6Shares fell 2.3% to US$4.16 after the announcement.