Energy Vault secures project financing and draws $27.2 million for Sosa

Energy Vault subsidiaries entered financing agreements on November 16, 2026, for the approximately 150 MW / 300 MWh Sosa battery project in Texas. The package includes a $78.0 million preferred-equity bridge facility and an $8.7 million letter-of-credit line, of which Energy Vault drew $27.2 million on November 19, 2026. A third-party investor committed $79.6 million to the project, while OIC provided $38.3 million to Asset Vault and received warrants covering up to 6,089,009 Energy Vault shares.

The financing provides construction capital but adds secured repayment obligations, with the bridge borrowings due no later than April 1, 2028. The OIC warrants could dilute existing shareholders if exercised, and the investor funding remains subject to project and tax-credit conditions.

  • 1The Sosa project is approximately 150 MW / 300 MWh and is located in Madison County, Texas.
  • 2Energy Vault drew $27.2 million on November 19, 2026, under the bridge facility.
  • 3The financing includes a $78.0 million preferred-equity bridge facility and an $8.7 million letter-of-credit facility.
  • 4A third-party investor committed $79.6 million for Class A membership interests in the Sosa Partnership, subject to funding conditions and installments.
  • 5OIC contributed $38.3 million to Asset Vault, and Energy Vault issued warrants to purchase up to 6,089,009 common shares at $4.080375 per share.
  • 6The bridge borrowings mature no later than April 1, 2028.

Sources