AI data‑center power crunch fuels rapid expansion of U.S. fuel‑cell market

U.S. hyperscalers are turning to on‑site fuel‑cell generators to avoid long grid connection times for AI data centers. Rystad Energy estimates spending on such fuel‑cell systems will climb to roughly $30 billion by 2030, up from about $2.8 billion in 2025. Bloom Energy reported third‑quarter revenue of $1.24 billion, a 138 % jump, and lifted its 2026 revenue outlook to $4.4‑$4.6 billion, while Oracle has earmarked up to 2.8 GW of Bloom fuel‑cell capacity, with 1.2 GW already secured. FuelCell Energy expects data‑center work to represent 75‑85 % of its revenue within the next two to three years.

Bloom Energy’s higher revenue guidance and the sizable Oracle contract suggest a near‑term earnings boost for the company, which could lift its stock. The projected industry spend and order book of about 9 GW indicate a growing market for fuel‑cell suppliers, but investors should watch supply‑chain and permitting constraints that could limit growth.

  • 1Rystad Energy projects fuel‑cell spending for data centers to reach about $30 billion by 2030, up from an estimated $2.8 billion in 2025.
  • 2Bloom Energy’s third‑quarter revenue rose 138 % to $1.24 billion.
  • 3Bloom posted net profit of $250.3 million, reversing a loss of $23.1 million a year earlier.
  • 4The company raised its 2026 revenue outlook to a range of $4.4 billion to $4.6 billion.
  • 5Oracle plans to acquire as much as 2.8 GW of Bloom fuel‑cell systems, with 1.2 GW already contracted.
  • 6FuelCell Energy expects data‑center and related business to account for 75‑85 % of its revenue within two to three years, up from 25‑30 % today.