NRC grants construction permit for Dow‑X‑energy four‑reactor Xe‑100 project in Texas
The U.S. Nuclear Regulatory Commission issued a construction permit on Nov. 9, 2026 for four Xe‑100 high‑temperature gas‑cooled reactors at Dow’s Long Mott Generating Station in Texas. Each unit is rated at roughly 80 MW of electricity and 200 MW of thermal output, for a total of 320 MW electric and 800 MW thermal capacity. The permit clears a key regulatory hurdle, but Dow must still make a preliminary investment decision in 2027 and obtain a separate operating license before construction can begin.
Why it matters
The permit signals regulatory approval for the first high‑temperature gas‑cooled reactor at an industrial site in decades, but Dow has not committed capital; construction depends on a 2027 investment decision and a later final decision. If approved, the reactors could supply low‑carbon power and steam to Dow’s plant, potentially reducing its energy costs over a projected 60‑year lifespan.
Key facts
- 1The NRC issued the construction permit on Nov. 9, 2026. newscord.org
- 2The project will consist of four Xe‑100 reactors, each designed for about 80 MW electric and 200 MW thermal output. finance.yahoo.com
- 3Combined, the reactors would deliver 320 MW of electricity and 800 MW of thermal output. newscord.org
- 4Dow expects to weigh a preliminary investment decision in 2027, with construction only after a final decision. xenospectrum.com
- 5The Department of Energy’s Advanced Reactor Demonstration Program has committed up to $2.15 billion in support for the project. newscord.org
- 6Construction could begin later this decade, with initial energy delivery targeted for the early 2030s. finance.yahoo.com