Oracle agrees to take Point Beach nuclear power for Wisconsin data center
Oracle reached a conditional agreement with We Energies to take 125-250 megawatts of Point Beach nuclear generation for its Project Lighthouse data center campus in Wisconsin. Oracle would assume roughly $300 million of fuel costs that would otherwise fall on We Energies customers. The arrangement requires approval from the Wisconsin Public Service Commission.
Why it matters
Oracle says it will cover the rising energy costs associated with the arrangement, which is intended to reduce ratepayer exposure while supplying its planned data center. The transaction remains conditional on state regulatory approval.
Key facts
- 1Oracle's planned purchase covers 125-250 megawatts from the Point Beach Nuclear Plant. wpr.org
- 2We Energies and Oracle expect the agreement to provide $300 million in customer savings. wpr.org
- 3The proposed arrangement is subject to approval by the Public Service Commission. urbanmilwaukee.com
- 4Oracle is developing the $15 billion Lighthouse data center campus with Vantage Data Centers and OpenAI. wpr.org
Open questions
- The Public Service Commission has not yet approved the agreement.
- Material 3 reports a projected delay to the data center's energisation schedule, citing Aterio, but this projection is not confirmed by Oracle or the regulator.