Baker Hughes secures ~1.1 GW power and cooling order for U.S. tech AI project

Baker Hughes announced it won an integrated power‑generation and cooling contract from a major U.S. technology company. The deal calls for 34 Frame 5 gas turbines, nine NovaLT‑16 turbines, generators, gearboxes and Chart dry coolers to deliver about 1.1 GW of reliable power for AI computing. The power‑generation portion was booked in Q3 2026 and the cooling equipment in Q4 2026.

The order adds to Baker Hughes' backlog and will generate revenue in the later 2026 quarters, supporting the company's growth in AI‑related energy solutions.

  • 1The contract provides approximately 1.1 GW of power generation capacity.
  • 2It includes 34 Frame 5 gas turbines and nine NovaLT‑16 turbines.
  • 3Chart dry coolers are part of the cooling system for the AI workloads.
  • 4The power‑generation order was booked in the third quarter of 2026.
  • 5The cooling‑equipment order was booked in the fourth quarter of 2026.