Empire Wind Now Expected to Deliver First Power in 2027 as Jones Act Vessel Delays Push Back Turbine Installation
Equinor's Empire Wind project off New York faces a delay, with first power now expected in early 2027 due to Jones Act vessel requirements. The 810-MW project is 80% complete, with turbine installation delayed. Equinor maintains a $7.5B budget and $2.5B in tax credits, with no change in spending or timing. The delay follows previous regulatory hurdles, including a court case that was dismissed in September 2026.
How this was made

The 30-second read
Why it matters
The schedule shift does not alter the $7.5 billion budget but moves some spending into 2027, affecting cash‑flow timing.
Market read
The delay is a material project update for a large U.S. offshore wind asset, but its impact on Equinor's stock is likely limited to short‑term sentiment.
What to watch
Potential for future policy incentives or tax credit extensions that could improve project economics.
Background
Equinor reported its Q3 2026 results alongside the Empire Wind schedule update, noting the project is 80% complete.
Ticker impact
Equinor announced its Empire Wind offshore wind project will deliver first power in 2027 due to delays with U.S.-built support vessels.
potential downward pressure as investors price in later revenue from the wind farm.
Project delays affect future cash flow timing; no offsetting positive news was provided.
Market effects
May raise concerns for offshore wind developers about U.S. vessel regulations.
Limited to New York renewable energy outlook.
Modest, as the project size is significant but isolated.
Counterpoint
Delay could allow cost optimizations and better turbine technology, mitigating impact.
Key entities
- CompanyEquinor
Norwegian energy company developing the Empire Wind offshore wind project.
- CompanyMaersk Offshore Wind
Developer of the installation system using the foreign‑built vessel Maersk Viridis.