Talisker Announces Preliminary Economic Assessment for the Bralorne Gold Project Highlighting C$1.0 Billion After-Tax NPV5% and 31.3% IRR at a Base-Case Gold Price of US$3,500/oz; At US$4,300/oz Spot Gold, C$1.9 Billion After-Tax NPV5% and 67.2% IRR
Talisker Resources Ltd. (TSX: TSK, OTCQB: TSKFF) announced a Preliminary Economic Assessment for its Bralorne Gold Project, highlighting a C$1.0 billion after-tax NPV5% and 31.3% IRR at a base-case gold price of US$3,500/oz. At a spot gold price of US$4,300/oz, the NPV5% increases to C$1.9 billion with a 67.2% IRR. The project has a 14-year mine life with average annual production of 110,000 ounces of gold. Initial capital is estimated at C$416 million, with sustaining capital of C$782 million.