Rio Tinto signs 50 MW power deal to restart Line 4 at Tiwai Point, adding 30,000 t aluminium

Rio Tinto has entered a three‑and‑a‑half‑year, 50 MW electricity agreement with Contact Energy to bring Line 4 at the Tiwai Point aluminium smelter back into operation. The restart is slated for October 2027 with full production by December 2027, adding roughly 30,000 tonnes of aluminium per year and restoring the plant to about 360,000 tonnes capacity. The company says the extra output could generate around NZ$100 million of additional export revenue at current spot prices.

The additional 30,000 t of aluminium increases Rio Tinto’s Australia‑New Zealand smelting capacity by about 3 %, potentially boosting the group’s revenue stream. The NZ$100 million export‑revenue estimate provides a concrete near‑term financial benefit for the company and New Zealand’s economy.

  • 1Rio Tinto signed a three‑and‑a‑half‑year, 50 MW electricity agreement with Contact Energy.
  • 2The restart of Line 4 is expected to add approximately 30,000 tonnes of aluminium per year.
  • 3Full production is planned for December 2027 after an October 2027 restart.
  • 4The restart would restore the smelter’s capacity to roughly 360,000 tonnes per annum.
  • 5Based on current global spot aluminium prices, the extra output could generate around NZ$100 million in additional annual export revenue.
  • 6The agreement reduces electricity supply to 25 MW during winter months to protect New Zealand’s broader energy security.