Koryx Copper Announces Pre-Feasibility Results for the Haib Copper Project, Southern Namibia
Koryx Copper (TSXV: KRY) announced pre-feasibility results for its Haib Copper Project in Namibia. The project has probable reserves of 3 million MT of contained copper and is expected to produce 135,000 MT of copper annually in the first 10 years. The project has an after-tax NPV8% of $2.5 billion and a post-tax IRR of 25%. The company plans to complete the definitive feasibility study by early 2027 and commence construction in 2028.
How this was made

The 30-second read
Why it matters
The disclosure provides detailed techno-economic metrics (NPV/IRR, costs, recovery, production rates) and a forward-looking schedule for permits, DFS, and potential early works, which can shift perceived probability of project advancement and financing readiness.
Market read
For traders in copper development equities, the PFS is a sentiment and probability catalyst, but it remains pre-DFS and pre-construction, so follow-through depends on permitting, financing, and DFS outcomes.
What to watch
Financing terms and offtake arrangements are not disclosed here; also, the energy mix (solar plus battery) and water sourcing plan could face cost or schedule risk during detailed engineering.
Background
Koryx Copper S.A. reports Pre-Feasibility Study results for its wholly owned Haib Copper Project in southern Namibia, including production profile, costs, and permitting/DFS milestones.
Ticker impact
Koryx announces Haib Copper Project PFS with base-case economics, including post-tax NPV8% of US$2.5bn and IRR of 25%, plus permitting and DFS timeline.
Likely positive bias as traders price higher probability of progressing to DFS and early works, tempered by remaining permitting and financing execution risk.
The article is a first disclosed PFS with detailed cost and production metrics, plus targeted permit completion by mid-2027 and early works late-2027. However, it still requires DFS completion, financing, and final approvals before capex.
Market effects
Adds another copper development project with quantified costs, recovery, and energy/water plans, which can marginally support sentiment for copper project pipeline quality.
Highlights Namibia permitting and infrastructure approach (NamPower connection, solar plus storage, Orange River water), which may be read as reducing execution friction for future regional projects.
Does not change global supply immediately, but contributes to the long-dated narrative around copper availability and project economics under $5/lb Cu assumptions.
Counterpoint
PFS results can be optimistic; traders may discount them until DFS confirms capex, recovery, and permitting timelines, especially given the large upfront build capex and sustaining capex assumptions.
Key entities
- companyKoryx Copper S.A.
Announces PFS results for the Haib Copper Project and outlines next steps toward DFS, permitting completion, and early works.
- projectHaib Copper Project
Wholly owned porphyry copper deposit development plan in southern Namibia with Cu, Mo, and Au by-products.
- utilityNamPower
Referenced for the 220kV overhead powerline connection to Harib substation.
- water authorityNamWater
Referenced via a signed MOU for water supply sourcing from the Orange River system.